2017 Emergency Pavement Repair Project

Due to the extreme winter weather this year, many streets suffered from frost damage.  During severe ground freezes and thaws, road surfaces are damaged as the ground expands and contracts, causing frost heaves and potholes. This project will remove and replaced the damaged road surfaces on several streets and is made possible due to a $50,000 grant award from the Transportation Improvement Board via its Emergency Repair Program.

News and Information

  • City Crews Start Work Tuesday, July 11th
  • 2017 Emergency Pavement Repair Project Traffic Revisions – August 7th through August 11th

Bid Process

Bids were solicited from contractors listed on the City’s Small Works Roster as having experience and qualifications to perform the work.